{" "} Network Diagram Data for a Minor Project

Network Diagram Data for a Minor Project

Activity

Initial Node

Final Node

Est. Time

A

1

2

1

B

1

4

3

C

1

3

1

D

2

4

2

E

3

6

2

F

4

5

1

G

4

6

3

H

5

7

2

I

6

7

4

J

7

8

2

The estimated time is in days. The network proceeds are from Node 1 to Node 8. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. Supply the following information:

1. Identify all the paths on the network diagram and note the estimated time for each.

2. Identify the critical path for this project. How long is the path?

3. What is the shortest time it will take to complete this project?

4. Identify which, if any, nodes have bursts or are merges.

5. Identify any tasks that appear to be in parallel. What factors should a project manager consider when working with parallel tasks?

Improve Your Grades with Custom Writing Help
Homework Help
Writing Help
Editing Services
Plagiarism check
Proofreading services
Research Project help
Custom writing services
scanner
E learning blogs

Disclaimer : The study tools and academic assistance/guidance through online tutoring sessions provided by AssignmentHelp.Net is to help and enable students to compete academically. The website does not provide ghostwriting services and has ZERO TOLERANCE towards misuse of the services. In case any user is found misusing our services, the user's account will be immediately terminated.