You are capturing the time security team engaged the job site
Adding Activities and Relationships
Use these in the case where an activity needs to report when it finishes, not its progress or Start date.
About 80 percent of the schedule activities are designated as this type in a typical schedule. Therefore, the most common Activity Type default should be task dependent.
Resource dependent
![]() |
In the case of a non-labor resource, to schedule accurately, the resource | |
---|---|---|
calendar needs to be up-to-date and indicate that resource's availability | ||
in terms of working time and non-working time. Material resources do | ||
[ 122 ]
Chapter 5
A good example is security. If you are capturing the time a security team is engaged on the job site, you would tie the Start Mobilization at Job Site Start Milestone activity as a predecessor to the Monitor Security of Job Site activity, and place a Finish Milestone (Complete Job Site Removal) as the successor.