What the project length and total budget develop network diagram help you out
c. It is the end of phase D in month 48 and the following table represents the actual progress of the activities in the project. What are the values for CPI, SPI, EAC, ETC, CV, SV and VAC? (3)
N.B. For the forecasting model, assume the existing CPI and SPI work well for the remaining works as well.
| Act | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| % com May | 100 | 100 | 0 | 0 | 0 | 0 | 0 |
| % com June | 100 | 100 | 100 | 20 | 0 | 0 | 0 |
| % com July | 100 | 100 | 100 | 100 | 0 | 0 | 0 |
Part B) Based on the July progress, when is the project likely to finish?Calculate EAC(t) and ETC(t)(3)
How much is it likely to cost at the end? Calculate EAC & ETC. Analyze the results in details. Use three calculations of optimistic, pessimistic & most likely as per lecture notes and class exercises.