The signal design will use the nema standard phase order
|
Spring 2021 |
|---|
Traffic Impact Analysis of a New Grocery Store
foot retail grocery market. This new grocery store is going to open in summer 2023.
Map
2PROJECT OF TRAFFIC IMPACT ANALYSIS
•Analyze performance of the intersection N. McCarran Blvd and Evans Ave that will be influenced by the grocery store.
Task 1 Project management
You are encouraged to form a group of two members to work on the technical tasks of the project, data analysis and produce a final report. You must clearly state the percentage contribution by each team member in your report. Your project grading will be based on the report and the contribution percentage.
2
|
Spring 2021 |
|---|
Task 3.3 Forecast the future traffic volumes (2023) based on the traffic growth rate. Due to normal growth of the Reno metropolitan area, the traffic demands at the study intersections have been growing and will grow at a rate of 2% per year. Therefore, the traffic demands at the intersections will be higher than the existing even without the proposed grocery store (the traffic demands in 2023 without the project-generated traffic is referred to as the background traffic conditions).
Task 3.4 Forecast the intersection traffic volumes generated by the new store.
in Figure 1.
Task 3.5 Estimate intersection traffic volumes in 2023 by combining volumes
|
Spring 2021 |
|---|
Task 4 Signal timing design
Task 7 Final report (a Word file submitted through Webcampus and a
hard copy)
4)Signal timing design
5
6