Project
Management

Dr. Ron Lembke

• Never done one exactly like this

• Many related activities

Why are projects hard?

• Resources-
– People, materials
• Planning
– What needs to be done?

IT Projects

• Half finish late and over budget
• Nearly a third are abandoned before completion
– The Standish Group, in Infoworld

• Establishing objectives
• Determining available resources• Sequencing activities
• Identifying precedence relationships• Determining activity times & costs• Estimating material & worker
requirements
• Determining critical activities

• PERT by U.S. Navy for Polaris missile

• Consider precedence relationships & interdependencies

• On schedule? Within budget?

• Probability of completing by ...?

PERT & CPM Steps

• Identify activities
• Determine sequence
• Create network
• Determine activity times
• Find critical path
• Earliest & latest start times • Earliest & latest finish times • Slack

Receive diploma

1

2 3
1 month 4? Years 1 day
Enroll

Attend class, study, etc.

3

4

AoA Nodes have meaning

2 3 4
Applicant

Aluma
Alumnus

Precedence Relationships – Scenario 1a

• Big-picture sequence easy:

D

– Demolition

After: W D

– Drywall, tape & texture

– Slate flooring

• Gantt chart

• Critical Path Method (CPM)

Activity

Time Period
J J F F M M A A M M J J J J

Design Build
Test

You are viewing 1/3rd of the document.Purchase the document to get full access instantly

Immediately available after payment
Both online and downloadable
No strings attached
How It Works
Login account
Login Your Account
Place in cart
Add to Cart
send in the money
Make payment
Document download
Download File
img

Uploaded by : Joshua Miller

PageId: ELIE26C8A6