Requirements prioritized and approved solution options false
1. Followings are some input and output for solution assessment and validation tasks.
Write down whether they are input or output and also specify the task name
a. Requirements (Prioritized and Approved, Solution (Designed), Solution Scope
Input - Allocate Requirements
b. Requirements (Allocated)
Output - Allocate Requirements
c. Business Requirements, Identified Defects, Solution (Deployed), Solution Performance Metrics
Input - Evaluate Solution Performance
d. Identified Defects, Mitigating Actions, Solution Validation Assessment
Output - Validate Solution
d. Validate Solution Inputs
2.3 Requirements (Prioritized and Validated), Solution (Constructed) a. Validate Solution Outputs
3. True/False Questions
a. Define Transition Requirements Outputs → Organizational Readiness
Assessment, Requirements (Stated), Solution (Deployed), Solution
(Designed)
False
b. Assess Proposed Solution Inputs → Assumption & Constraints,
Requirements (Prioritized and Approved) Solution Options
True
c. Define Transition Requirements Inputs → Transition Requirements
False
d. Assess Proposed Solution Outputs → Assumption & Constraints,
Requirements (Prioritized and Approved) Solution Options
False
4. What are the 3 types of requirements
traceability? Backward traceability (derivation)
Forward traceability (allocation)
Relationship to other requirements
7. Maintain requirements for reuse yields what output?
Traced requirements
True
10. Which document determines how the business analyst shares requirements
Coverage matrix
12. You are a business analyst tasked with ensuring that stakeholders with approval
such as requirements in which participants look out for errors or omissions
Structured Walkthrough
16. What is the basis of requirements management during a project which ensures that proposed requirements support business goals and objectives?
Structured Walkthrough
19. Which roles are involved in approving requirements? Domain SMEs, Implementation SMEs & Sponsor
20. Jen is experiencing a lot of ambiguity with some of the requirements that she has received from her stakeholders. What is a good technique that can be used to resolve these ambiguities?
23. What role does the sponsor play in the Manage Solution Scope and Requirements task? The business case, solution or product scope and all requirements must be reviewed and approved by the sponsor(s) according to the approval authority stated in the requirements management plan.
24. List the downstream tasks from the manage solution scope
and requirement task. maintain requirement for reuse
assess proposed solution
allocate requirement
27. When preparing the requirements package, how will the BA know the stakeholder's communication needs?
by referring to the Business Analysis communication plan
Business analysis communication plan