Itc505 ict project management: application development project
ITC505 ICT Project Management: Application Development Project
Case study – Social Media Research Centre
During a meeting with his boss (David Wright), Bruce has been asked to establish a researcher centre. The research centre, which will commence operations in February 2018 first as an informal research group, should be established by June 2017. Alex’s decision to proceed with this major project is spurred by the fact that an associated organizational centre, which researches in a closely related area, has recently ceased operations. There is also a tremendous pressure from David’s senior executives to produce high quality research that is focused in nature. In fact one of David’s senior executives’ comments was that David’s Unit does not have a clear identity when it comes to its scholarly research output compared to the one in Australian National University. After several meetings with subject matter experts (consultants) and a rigorous analysis of the current trends in research in the area of information technology it has been decided that the most appropriate research area for the proposed research centre to focus on is social media. Fortunately several of David’s Unit staff are active researchers in this area. What made this direction even more attractive is that demand from Master and Doctoral students has been largely for programs in this area. David’s Unit also enjoys a very good relationship with an international expert Craig Bamworth in the social media area who has kindly agreed to offer his expertise to Bruce (the program manager).
One of the projects within the Social Media Research Centre larger project that Bruce has identified as important is the development of a web application for the proposed centre.
Your manager, Bruce has given you guidance that the project needs to be completed within 8 months and that costs should be minimised wherever possible with given budget of AUD 50000.00
Task 1: Prepare Project Charter
Basic details Including: Title of the project, Name and email of the Project Manager (yourself), Duration of the project, and High level budget
MOV - Measurable Organisational Value
Task 2- Communication Plan
Answer:
Project Charter
Date: 5th May 2017
Title of the Project: Web Application Development Project
Information of the Budget
Project of Web Application Development
Analysis of requirement
Project Manager
Formation of Project Plan
Planner
Commencement of the Project
Analysis of design requirement
Software Development
Making of design outline
Software Development
Completion of Design Phase
Programming requirement analysis
Programmer
Application programming
Programmer
Coding Phase
Selection of suitable coding method
Coder
Completed of coding phase
Alignment of design, code and the program developed
Tester
Review of the application
Tester
Testing of the function
Tester
Final Review and Documentation
Final modification
Software developer, programmer and coder
Signing of the documents
Project manager, business analysts
Objective of the Project:
- The project was developed to form a appropriate project plan to develop and implement a web based application for the various operations of the Social Media research centre. The project would be helpful to make the various processes of the organization easy. Modification and development of operations are two major influencers of this research process.
- The main scope of this project is the modification of system requirement. The web based application would be helpful to store the research done by the organization. It would be a helpful tool in accessing their research and in forming of their own analysis with the help of stored data and information in the system.
- The primary deliverable of the project is the development of a web-based system for the organization. A database server would be connected to the application. It would allow the students to resister in the application to access the data and information.
- The major benefit of the development of this kind of system is that it would help the students in their study. The modified system would assist the students by providing data and information.
The use of change evaluation and implementation would not be included in this project. The change management is an important factor in invoking the development of strategies and tools to carnage the project.
MOV - Measurable Organisational Value
MOV Statements: The MOV statement is shown below:
2nd – Operational
3rd – Customer
- Better- The main objective behind the development of this project is to make process of searching necessary data and information easy for the students of Social Media Research Centre.
- Faster – The clients requires the efficiency of the operations of the organization. It would assist the students to search for the relevant data and information for their study and research purposes.
- Cheaper – The modification of the operations of the project is the purpose of scheduled project management operations.
- Do More – The clients had been attempting the development of the operations of the project.
- To evaluate the expected cost and its flow after implementation, the process of cost analysis would be used.
- Net Present Value would be used to get the internal rate of return (IRR)
Assumptions and Constraints
- Any assumption made at the time of the project
List of constrains that need to be addressed
List of the Stakeholders
| Stakeholder No. | Name & Signature | Role and Responsibility | Position | Contact Information |
| 1 | <<name of the Student>> |
To manage the project operations | Project Manager | |
| 2 | Percy Marwin
|
To develop the software interface and to implement the project operations | ||
| 3 |
Josh Keller |
To analyze the various project requirements | ||
| 4 |
Iris Bin |
To make codes for the development of webpage application | ||
| 5 |
Chang Lee |
To program operations for webpage application | ||
| 6 |
Yuki Hosire |
To manage the database of the project | ||
| 7 |
Terry James |
To test different functions of the webpage | ||
| 8 |
Hawkins Mathews |
To develop the budget of the project | ||
| 9 |
Stuart Jones |
To make the plans to complete the project | ||
| 10 |
Lauren Nath |
To analyze the security aspects of the webpage | Security Analysts |
Communication Plan Template
Purpose of the Plan: In order to form a operability and effective plan for the project operation, the communication plan is a helpful tool. To convey one’s idea and the development of more systematic plan is the main reason behind the development of communication plan. To complete the project objectives, the overall team philosophy plan is a helpful factor. The lateral communication depends on the hypothetical development of the plan. It helps to form functional and effective functional operation of the project. The downward communication plan shows the channeling of thoughts, ideas and messages. To form an effective and smart communication plan, the upward communication is an important factor.
- Work division of the project
- Effective implementation plan formation
- Convey issues and to solve them
- Development of change requirements
| Stakeholder | Shared Information | Information exchange frequency | Information exchange location | Communication purpose | Communication mechanism |
| Who | What | When | Where | Why | How |
| Investor | Progress of project | Monthly | Board Meetings | For conveying the project progress | Face to face conversation and report |
| Project Manager | Progress or any issue in the project | Weekly | General Meetings | Getting the solutions of the issues | Report and Drafts |
| Quality Analysts | Performance efficiency outcome data | Fortnight | Online Platform | Providing quality review report | Report and Drafts |
| Developer | Model and design development | Once | Conversation through Email | Conveying design modeling software | Report and Drafts |
| Budgeter | Resource development and budget | Monthly | Conversation through Email | Forming budget for the project | Report and Drafts |
Bibliographies
Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC Press, LLC.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.