And brick veneer timber framed structure
CPCCBC4011B: Assessment 3
|
|
|
|
(Electronic Signature is accepted)
Note: OTEN has the right to reject your assessment if the above declaration has not been completed.
LA023653, Assessment 3, Marking guide, CPCCBC4011B, Edition number
4 © New South Wales Technical and Further Education Commission, 2019 (TAFE NSW), Version 2, November 2019 |
---|
You may make any assumptions you need to, but be sure to include them as part of your submission.
Task – Footing and flooring systems
1.Determine the location of the building in relation to other buildings and boundaries, and place the pegs in the ground marking the four corners of the building. You must make sure that the pegs are square by making the following check:
The distance between peg AA and peg BB is the same distance between peg CC and peg DD The distance between peg AA and peg CC is the same as the distance between peg BB and peg DD The distance between peg AA and peg DD is the same as the distance between peg BB and peg CC
LA023653, Assessment 3, CPCCBC4011B, Ed4 © New South Wales Technical and Further Education Commission, 2019 (TAFE NSW), Version 2, November 2019 |
|
---|
2.Structural integrity – study the drawings showing details of the
footings for this project. Describe how the footings – piers, pad
footings (these are really pile caps), strip footings (this is really a
pier and beam type system) and slab – contribute to the structural
integrity of the building. You will need to address the following in
your answer:
a. the purpose of each type of footing (the specific loads that are
supported; why this type of footing is used; how the loads are
transferred to the ground) (approx. 100 words each)
b. specific requirements for each type of footing (why they are the size specified; why they have reinforcement in the configuration shown; types of joints if applicable) (50 -100 words each)
1.) Spread (pad) footings:Spread footings are usually square or round, and support a
3.) piers :Where footings are used on fill, unstable soils (subject to slip), low bearing capacity
3.Once the layout of the footings has been accurately set out on the
site, construction of the footings can begin:
c. outline the construction method and sequence to construct each of
these footing types (approx. 100 words each)
d. what codes and/or Australian Standards are relevant to the compliance requirements for these footings? (briefly outline what each covers)
Pour concrete in the piers. The concrete is poured to approximately 500 mm below the NGL or FGL. No reinforcement is required in the pier holes. The concrete would be 20 MPa compressive strength.
After three days, excavate concrete beams between the piers. These concrete beams will
be excavated around the entire perimeter of the house.
LA023653, Assessment 3, CPCCBC4011B, Ed4 © New South Wales Technical and Further Education Commission, 2019 (TAFE NSW), Version 2, November 2019 |
---|
Codes and/or AS
NCC Vol 2, Part 3.2.5 Footing and Slab Construction
AS 2870–2011 Residential slabs and footings
AS 2159 & 3600 Concrete Pile Design
Construction method/sequence
Pile caps are constructed by excavating an area around the group of piles to enable form-work to be inserted. The pile tops may be trimmed to ensure they are at the same height. A reinforcement cage is then built and positioned in the formwork cast box and fastened to the piles.Strip footings
Codes and/or AS
NCC Vol 2, Part 3.2.5 Footing and Slab Construction
AS 2870–2011 Residential slabs and footings
Construction method/sequence
Excavate the pier holes. The number, location and spacing will be shown on the design engineer's drawings.Slab
Codes and/or AS
NCC Vol 2, Part 3.2.5 Footing and Slab Construction
AS 2870–2011 Residential slabs and footings
Construction method/sequence
Submission
Preparation
Information such as People-in-charge, inspection method, requirement reference, frequency, acceptance criteria, stages, and Records or status of every single work should be included in all the elements of each part.
4.Read about the different types of joints in ground slabs.
Isolation joints are common to road pavements to allow thermal expansion, in buildings it is
commonly placed between a column and a slab in the ground floor and in a factory temperature is
The first floor office floors are essentially also slabs, a structural member in pr-construction it
is supported by form-works and strengthened by reinforcement bars. In post construction it is
| Using the floor plan workers will assemble the desired form work for slabs/office floors. |
---|
Removing of forms
Detail the sequence of activities for the construction of the office floors(approx. 100 words)
COLUMN CASTINGS
SLAB CASTINGS
BCA volume 1, Clauses F 1.9 and F 1.10 relevant to damp-coursing:
F 1.9 Damp-proofing:
i. moisture from the ground must be prevented from reaching: the lowest floor timbers and the walls above the lowest floor joists; and the walls above the damp-proof course; and
ii. where a damp-proof course is provided, it must consist of - SA F1.9(b) :
a material that complies with AS/NZS 2904; or impervious termite shields in accordance with AS 3660.1.
LA023653, Assessment 3, CPCCBC4011B, Ed4 © New South Wales Technical and Further Education Commission, 2019 (TAFE NSW), Version 2, November 2019 |
|
---|
For Damp - flowing:
Arranging, Implementing, Checking, and Installation of Sodden - flowing: