job costing: applied overhead calculation answers and explanation
Job Costing: Applied Overhead Calculation Step by step Solution with Explanation
Your question:

XYZ Company uses a job order costing system and has established a pre-determined overhead rate of 145% of direct labor cost. Job #231 was charged with direct materials of $69,000 and had a total cost of $228,250.
Job Costing: Applied Overhead Calculation Answers and Explanation
Denote applied overhead cost as AO.
We know the pre-determined overhead rate is 145% of direct labor cost, which can be written as 1.45 * direct labor cost (DL).
Solve for DL:
Rearrange the equation to isolate DL:
Applied Overhead Cost:
Now that we have the direct labor cost, apply the predetermined overhead rate to find AO: